Published: 19 November 2026 | Updated: 26 November 2026Reading time: 9 minutesCDM 2015SI 2015/51

CDM 2015 Dutyholders Explained: Who Does What on a Construction Project

By TE Training Academy Editorial Team | Reviewed by Mehdi Hosseini, CEng FICE

Reviewed against: the Construction (Design and Management) Regulations 2015 (SI 2015/51) as reproduced in HSE L153, HSE's CDM 2015 dutyholder pages, the HSE Enforcement Policy Statement and GOV.UK guidance on the Building Regulations dutyholder regime

The Construction (Design and Management) Regulations 2015, known as CDM 2015, came into force on 6 April 2015. They apply to construction projects in Great Britain whether or not the project is notifiable, including work for householders. Rather than putting one person in charge of safety, they share legal duties between six dutyholders: the client, the principal designer, designers, the principal contractor, contractors and workers.

This guide sets out what each must do, with regulation numbers taken from the legal text reproduced in HSE’s guidance L153. It also covers F10 notification, the key project documents, welfare, the separate Building Regulations roles and HSE enforcement.

1

Client duties: commercial and domestic clients

A client is any person for whom a project is carried out (regulation 2). Under regulation 4, a commercial client must:

  • make suitable arrangements for managing the project, including sufficient time and resources, and maintain and review them (4(1) and 4(3));
  • make sure the arrangements allow the work to be done, so far as is reasonably practicable, without risks to health or safety, and that Schedule 2 welfare facilities are provided (4(2));
  • provide pre-construction information as soon as practicable to every designer and contractor appointed or being considered (4(4));
  • ensure a construction phase plan is drawn up before the construction phase begins and that the principal designer prepares a health and safety file (4(5));
  • take reasonable steps to ensure the principal designer and principal contractor carry out their duties (4(6)).

Where there is, or is likely to be, more than one contractor, the client must appoint a principal designer and principal contractor in writing (regulation 5). If it does not, it must carry out their duties itself (5(3) and 5(4)).

Domestic clients

A domestic client is one for whom the project is not carried out in the course or furtherance of a business (regulation 2). Under regulation 7, its duties in regulations 4(1) to (7) and 6 pass to the contractor, or to the principal contractor where there is more than one, unless the principal designer takes them on under a written agreement.

2

Designers and the principal designer

A designer is any person who, in the course of a business, prepares or modifies a design, or arranges for someone under their control to do so. Regulation 2 expressly includes clients and contractors when they design. Under regulation 9, a designer must:

  • not start work unless satisfied the client is aware of its duties (9(1));
  • apply the general principles of prevention and any pre-construction information to eliminate, so far as is reasonably practicable, foreseeable risks to people building, maintaining, cleaning or using the structure (9(2));
  • where risks cannot be eliminated, reduce or control them and pass information to the principal designer and the health and safety file (9(3));
  • provide enough information with the design to help others meet their duties (9(4)).

The principal designer

The principal designer is a designer with control over the pre-construction phase, appointed in writing where there is more than one contractor (5(1)(a)). Under regulations 11 and 12 it must:

  • plan, manage and monitor the pre-construction phase and coordinate health and safety matters during it (11(1));
  • identify and eliminate or control foreseeable risks, so far as is reasonably practicable (11(3));
  • ensure designers comply with regulation 9 and that everyone cooperates (11(4) and 11(5));
  • help the client provide pre-construction information (11(6));
  • liaise with the principal contractor and share information for the construction phase plan (11(7) and 12(3));
  • prepare and update the health and safety file and pass it to the client at the end of the project (12(5) to 12(10)).
3

Principal contractor, contractors and workers

The principal contractor is a contractor appointed in writing to control the construction phase where there is more than one contractor (5(1)(b)). Under regulations 12 to 14 it must draw up the construction phase plan before the site is set up and keep it under review (12(1) and 12(4)); plan, manage, monitor and coordinate the construction phase (13(1)); organise cooperation between contractors (13(3)); ensure a suitable site induction, prevent unauthorised access and provide Schedule 2 welfare facilities (13(4)); liaise with the principal designer and pass on information for the health and safety file (13(5) and 12(7)); and consult and engage with workers (regulation 14).

Contractors

Every contractor must plan, manage and monitor the work under its control (15(2)) and follow directions from the principal designer or principal contractor and the relevant parts of the construction phase plan (15(3)). It must only use people who have, or are gaining, the necessary skills, knowledge, training and experience (15(7)), provide supervision, instructions and information, including a site induction where needed (15(8) and 15(9)), prevent unauthorised access (15(10)) and meet Schedule 2 for its workers (15(11)). On a single-contractor project, it draws up the construction phase plan (15(5)).

Workers

Workers work for or under the control of contractors. HSE’s guidance says they must be consulted on matters affecting their health, safety and welfare, take care of their own and others’ safety, report anything likely to endanger anyone, and cooperate with other dutyholders. The reporting and cooperation duties are in regulations 8(5) and 8(4).

4

When a project must be notified (F10)

Under regulation 6(1), a project is notifiable if the construction work on a construction site is scheduled to:

  • last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project; or
  • exceed 500 person days.

The client must give notice in writing to HSE as soon as is practicable before the construction phase begins (6(2)). The notice must contain the particulars in Schedule 1, be clearly displayed in the construction site office where workers can read it, and be updated if necessary (6(3)). Certain railway work is notified to the Office of Rail and Road, and work on nuclear sites to the Office for Nuclear Regulation (6(4) and 6(5)).

HSE’s guidance in L153 adds some practical points:

  • every day on which construction work is likely to take place, including weekends and bank holidays, counts towards the period;
  • if a project becomes notifiable because its scope changes, the client must notify as soon as possible;
  • the client may ask someone else to submit the notice on its behalf;
  • the simplest route is HSE’s online F10 form.

Notification does not decide whether CDM 2015 applies. L153 states that its requirements apply whether or not the project is notifiable.

5

Pre-construction information, the plan and the file

↔ Scroll table horizontally to view all columns
DocumentWho is responsibleWhen it is neededRegulations
Pre-construction informationClient, assisted by the principal designerEvery project, as soon as practicable2, 4(4), 11(6)
Construction phase planPrincipal contractor, or the sole contractorEvery project, before the construction phase4(5)(a), 12, 15(5)
Health and safety filePrincipal designerProjects with more than one contractor4(5)(b), 12(5) to 12(10)

Pre-construction information is information in the client’s possession, or reasonably obtainable, that is relevant to the work and proportionate to the risks. It covers the project, its planning and management, and health and safety hazards, including design and construction hazards and how they will be addressed (regulation 2).

The construction phase plan sets out the health and safety arrangements, site rules and specific measures for any work in the Schedule 3 categories of particular risk (12(2)).

The health and safety file holds information likely to be needed to keep people safe during later work on the structure (12(5)). HSE’s guidance says it is only required where there is more than one contractor. A client who disposes of its interest in the structure must pass the file to the new owner (4(7)). For how these documents work with temporary works, see our guide to CDM 2015 temporary works duties.

6

Minimum welfare facilities under Schedule 2

Schedule 2 sets the minimum welfare facilities for construction sites. The client’s arrangements must ensure they are provided (4(2)(b)), the principal contractor must provide them throughout the construction phase (13(4)(c)), and each contractor must meet them for its own workers (15(11)). The schedule covers:

  • Sanitary conveniences: suitable and sufficient toilets at readily accessible places, ventilated, lit and kept clean, with separate rooms for men and women unless each is in its own lockable room.
  • Washing facilities: near toilets and changing rooms, with clean hot and cold, or warm, water (running so far as is reasonably practicable), soap and a means of drying, plus showers where the work or health reasons require them.
  • Drinking water: an adequate supply of wholesome drinking water, with cups unless it comes from a drinking jet.
  • Changing rooms and lockers: where workers wear special clothing and cannot change elsewhere, with seating, drying facilities where necessary and secure storage for clothing and personal effects.
  • Rest facilities: enough tables and seating with backs, somewhere for pregnant workers and nursing mothers to lie down where necessary, arrangements for preparing and eating meals, a means of boiling water and an appropriate temperature.

Because the principal contractor’s duty runs throughout the construction phase, facilities need to be in place from the start of work on site.

7

CDM roles versus the Building Regulations dutyholders

The Building Safety Act 2022 led to a second set of roles with the same names. The Building Regulations etc. (Amendment) (England) Regulations 2023 (SI 2023/911) added Part 2A, on dutyholders and competence, to the Building Regulations 2010. They came into force on 1 October 2023 and apply in England.

↔ Scroll table horizontally to view all columns
AspectCDM 2015Building Regulations Part 2A
PurposeHealth and safety of workers and anyone around the siteDesign and building work complying with building regulations
Where it appliesGreat BritainEngland
In force6 April 20151 October 2023
Principal designerPlans, manages and monitors the pre-construction phase for health and safetyPlans, manages, monitors and coordinates design work so designs comply
Principal contractorPlans, manages and monitors the construction phase for health and safetyPlans, manages, monitors and coordinates building work and must never accept non-compliant work

GOV.UK guidance explains that the CDM principal designer and principal contractor can also carry out these roles for building regulations purposes. If they are the same, the client must confirm this in writing to those it appoints. Where different organisations hold the roles, they need to work together and share relevant information. The competence requirements differ under each regime, so clients should check competence for each role separately.

8

How HSE enforces CDM 2015

HSE is the enforcing authority for most construction projects, with the Office of Rail and Road and the Office for Nuclear Regulation covering certain rail and nuclear work. Fire authorities enforce some fire-related requirements where a site is within premises occupied by others (regulation 36). HSE’s Enforcement Policy Statement lists the options open to inspectors:

  • written information and advice, which may include a warning that the dutyholder is failing to comply;
  • improvement notices, where a breach must be remedied within a set period;
  • prohibition notices, where there is a risk of serious personal injury, which can take immediate effect and do not need a breach of the law;
  • simple cautions (England and Wales only) and prosecution, or a report to the Crown Office and Procurator Fiscal Service in Scotland.

Failing to comply with a notice is itself a criminal offence. Where an inspector finds a material breach and says so in writing, HSE also charges a Fee for Intervention.

CDM 2015 does not name specific courses, but it does require competence (regulations 8 and 15(7)). Role-based training is one way to build and evidence it: SMSTS for site managers, SSSTS for supervisors, DRHS for directors, and our CDM Awareness course for anyone new to the regulations. See all our CITB courses.

9

Frequently asked questions

Does CDM 2015 apply to small projects and home improvements?

Yes. HSE’s guidance states that CDM 2015 applies whether or not a project is notifiable, and it covers work for domestic clients. On domestic projects the client duties pass to the contractor, the principal contractor or, under a written agreement, the principal designer (regulation 7). The paperwork should be proportionate to the risks, but every project still needs a construction phase plan.

Who has to submit the F10 notification?

The client, under regulation 6, as soon as is practicable before the construction phase begins. It applies where work will last longer than 30 working days with more than 20 workers at any one time, or will exceed 500 person days. HSE’s guidance says the client may ask someone else to submit it on its behalf. For domestic clients, the duty passes to another dutyholder under regulation 7.

What happens if the client does not appoint a principal designer or principal contractor?

On a commercial project with more than one contractor, the client must carry out the principal designer duties in regulations 11 and 12 and the principal contractor duties in regulations 12 to 14 itself (regulations 5(3) and 5(4)). For a domestic client, the designer in control of the pre-construction phase becomes the principal designer and the contractor in control of the construction phase becomes the principal contractor (regulation 7(2)).

Is a health and safety file needed on every project?

No. HSE’s guidance in L153 says a health and safety file is only required for projects involving more than one contractor. A construction phase plan, by contrast, is required on every project. On single-contractor work the contractor draws it up (regulation 15(5)); otherwise the principal contractor does (regulation 12(1)).

Can one firm be principal designer under both CDM 2015 and the Building Regulations?

Yes. GOV.UK guidance says the CDM principal designer and principal contractor can also carry out those roles for building regulations purposes, and the client must confirm this in writing when they are the same. The competence requirements differ between the two regimes, so the client should check the appointee is competent for each role separately.

10

Sources

CDM 2015 Awareness Training

Understand your role under CDM 2015

Book TE Training Academy’s one-day CDM Awareness course to build your understanding of the regulations and the duties of each dutyholder.

  • Duration: 1 day
  • Certificate: TE Training Academy Certificate of Achievement, certified by Tunnel Engineering Ltd
  • Next steps: CITB SSSTS, SMSTS and DRHS courses for supervisors, managers and directors
Call our course advisors: 01732 247780Email: hello@tetrainingacademy.co.uk