Published: 18 November 2026Reading time: 8 minutesTBM tunnellingBS 6164:2019

Tunnel Boring Machines Explained: Types, Ground Conditions and Safety

By TE Training Academy Editorial Team | Reviewed by Mehdi Hosseini, CEng FICE

Reviewed against: DAUB Recommendations for the Selection of Tunnel Boring Machines (2022, revised 2025), BS 6164:2019 (BSI summary), PAS 8810:2016, the Work in Compressed Air Regulations 1996 and the ICE paper on Crossrail's machine-driven tunnels

A tunnel boring machine (TBM) excavates the ground, supports it and, in most modern machines, builds the tunnel lining as it advances. The German Tunnelling Committee (DAUB), the German member of the International Tunnelling and Underground Space Association, classifies TBMs as full-face machines, which excavate the whole cross-section with a cutterhead, or partial-face machines, which use an excavator arm or roadheader inside a shield.

This guide explains the main full-face machine types, how engineers choose between them, how the lining and back-up work, the hazards on a TBM drive and how TBMs have been used on three recent UK projects.

1

Rock machines: gripper, single-shield and double-shield TBMs

Three machine types are used where the face will stand up without active support. DAUB describes them as follows.

Open (gripper) TBM

Gripper TBMs work in rock with a medium to long stand-up time. They have no full shield and give no active support to the face. To push the cutterhead forward, hydraulic gripper plates brace against the tunnel wall; at the end of each stroke the machine rests on a rear support while the grippers are reset. Disc cutters break the rock, and support such as anchors, steel arches or sprayed concrete is installed close behind the cutterhead.

Single-shield TBM

A single (or open) shield is used for stable faces, for example firm clays or rock. The shield protects the excavation, a segmental lining ring is built inside it, and thrust cylinders push off the last completed ring.

Double-shield TBM

A double shield has two telescopic parts: a front shield with the cutterhead and main thrust cylinders, and a gripper shield behind it. In stable rock the grippers take the thrust, so the segment ring can be built while the machine bores. Where the grippers cannot hold, the machine works in single-shield mode and thrusts off the segments.

Cutting rock produces dust, so DAUB says these machines need dust suppression, such as water sprays at the cutterhead, a dust shield and extraction with dedusting on the back-up.

2

Closed-face machines: EPB, slurry, Mixshield and variable density

In soft ground, and especially below the water table, the face has to be supported actively. Closed-face machines seal the excavation chamber behind the cutterhead with a pressure bulkhead and keep it under pressure.

  • Earth pressure balance (EPB): the excavated soil itself, remoulded into a paste in the chamber, supports the face. A screw conveyor removes it, and the support pressure is controlled through the screw speed, the advance rate and the injection of conditioning agents such as foam, bentonite or polymers. DAUB notes that the proportion of fine particles in the ground strongly affects how well this works.
  • Slurry: a pressurised bentonite suspension supports the face, and the spoil is pumped to a separation plant on the surface. The support pressure can be controlled precisely with an air cushion behind a submerged wall. Herrenknecht calls its machines built on this principle Mixshields and lists sandy and gravelly soils and mixed ground with high permeability and water pressure as their field of use.
  • Variable density (VD): combines the slurry and EPB principles in one machine. The density in the chamber can be varied between the two, and the mode can be changed without conversion work.
  • Hybrid or multi-mode: the conveying system can be changed, for example from screw conveyor to belt; DAUB notes that the conversion usually takes several shifts.

An EPB machine can also run in open mode in stable ground, or in a transition mode with a partly filled chamber and compressed air. DAUB recommends that the machine type and operating mode are set for each section of the route, with a support pressure range for closed mode.

3

Microtunnelling and pipe jacking

For utility tunnels and pipelines, the lining is often pushed into place rather than built. The International Society for Trenchless Technology defines a pipe jack as a system of installing pipes directly behind a shield machine by hydraulic jacking from a drive shaft, so that the pipes form a continuous string in the ground. Microtunnelling uses the same method with a steerable, remotely controlled shield, at diameters too small for people to enter.

BS 6164:2019 covers pipe and box jacking in its clause on excavation and control of ground movement. In 2024 the Pipe Jacking Association replaced its earlier designer guidance with Pipejacking design guidance for CDM Duty Holders, based on consensus with the British Tunnelling Society and intended to be read with BS 6164. Tunnels and Tunnelling’s summary reports that it rates excavation methods by risk against internal diameter and drive length: machines operated remotely from the surface are the lowest-risk option, while methods that need people to enter the smallest pipes are classed as not acceptable.

The guidance also notes that meeting these safety requirements may call for a larger internal diameter than the hydraulic design alone would need, and it prefers intermediate shafts to in-tunnel tool changes on small machines.

4

Segmental linings and the back-up train

A shielded TBM builds the lining in rings of precast concrete segments, placed by an erector inside the tail of the shield, and the gap between the ring and the ground is filled with grout. Crossrail’s running tunnels show a typical arrangement. According to the ICE paper on the project’s machine-driven tunnels:

  • the excavated diameter was about 7.1 m, giving a lining with a 6.2 m internal diameter;
  • each 1.6 m ring had seven segments plus a small key;
  • segments were 300 mm thick, steel-fibre-reinforced C50/60 concrete, with gaskets sealing against groundwater pressures of up to 4 bar;
  • vacuum erectors placed the segments, and grout was injected through the TBM skin.

For design, PAS 8810:2016, Tunnel design – Design of concrete segmental tunnel linings – Code of practice, brings segmental lining guidance into one document. It excludes sprayed concrete and cast in situ linings, pipe jacking, and drill-and-blast and hard rock tunnelling.

The back-up train is the line of trailing gantries behind the shield that carries the equipment the machine needs to keep advancing. On modern drives it is long: each of HS2’s Chiltern tunnel machines was about 170 m long overall. On gripper machines, DAUB says rock support is completed in the back-up area and dust is extracted there. On the HS2 Chiltern drives, refuge chambers were provided on the TBMs as well as in the tunnel.

5

Choosing a machine: geology, groundwater and settlement

Machine selection starts with the ground. DAUB’s recommendations set out a step-by-step process:

  1. analyse the geotechnical report and the expected behaviour of the ground, the machine and any structures within the tunnel’s zone of influence;
  2. pre-select suitable machine types for each zone of similar ground by elimination;
  3. check how the spoil will be conveyed and then reused or disposed of;
  4. fix the machine type and divide the route into tunnelling sections, each with a defined operating mode.

Groundwater is often decisive. On Crossrail, six of the eight TBMs were EPB machines and two were slurry machines for the water-bearing Chalk aquifer. On HS2’s Chiltern tunnel, the contractor chose variable density machines because conventional low-density slurry could leak into fractures in the chalk and pollute the aquifer.

Settlement shapes how tightly the face is controlled. Crossrail assessed more than 17,500 third-party assets, generally specified 1.0% volume loss for the running tunnels and set tighter control zones of 0.5% or 0.75% in sensitive areas. The British Tunnelling Society’s guideline Closed-face tunnelling machines and ground stability (2005), published with the ICE, deals with choosing between EPB and slurry machines and managing ground stability in urban areas.

6

Main hazards on a TBM drive

The main hazards on a TBM drive, and where the guidance deals with them, are:

  • Segment handling: segments are lifted, moved and placed many times on every ring, in a confined space, so lifting plans, exclusion zones around the erector and clear communication matter. BS 6164:2019 brings guidance on materials handling into a single clause.
  • Cutterhead interventions: inspecting or changing cutting tools on a closed machine can mean entering the excavation chamber under compressed air through the machine’s air lock. That is work in compressed air under the Work in Compressed Air Regulations 1996. BS 6164:2019 now covers high-pressure compressed air interventions, supported by ITA/BTS Report 10, last revised in 2024.
  • Ventilation and air quality: Crossrail’s air quality guide lists quartz dust, strata gases, oxygen-deficient air and diesel exhaust from locomotives among the hazards on TBM drives.
  • Fire: BS 6164:2019 gives guidance on fire suppression for TBMs and other plant. In May 2022, after a vehicle fire in an HS2 Chiltern tunnel drive, three people on the TBM stayed in its refuge chamber for more than 12 hours until it was safe to walk out; nobody was injured.
  • Muck haulage: on Crossrail, spoil travelled by conveyor on the EPB drives and through pumped lines on the slurry drives, and sticky London Clay caused conveyor failures. Crossrail also produced a best practice guide on construction railway movements, noting that PUWER and CDM Part 4 apply.

Our CITB Tunnelling Safety Training Scheme course introduces tunnelling plant, the control of underground plant and emergency arrangements for people starting work underground.

7

Three UK examples

  • Crossrail (Elizabeth line): eight TBMs built 42 km of tunnels over about three years, with the final machine arriving at Farringdon in May 2015. Six were EPB machines, working mainly in London Clay and the Lambeth Group, and two were slurry machines for the Chalk.
  • Thames Tideway Tunnel: six TBMs built London’s 25 km “super sewer”: four for the main tunnel and two for connection tunnels in Wandsworth and Greenwich. Tideway announced in March 2024 that the underground civil engineering was complete.
  • HS2 Chiltern tunnel: two 10.26 m diameter variable density machines, Florence and Cecilia, bored the twin-bore tunnel of about 10 miles through chalk and flint. They broke through in February and March 2024, each having installed about 56,000 precast segments.

In each case the machine type followed the ground and the groundwater.

The Online Tunnel Engineering Course covers TBM tunnelling and pipe jacking in more depth, and our tunnelling courses page lists all our tunnelling training.

8

Frequently asked questions

What is the difference between an EPB and a slurry TBM?

Both support the face under pressure. An EPB machine uses the excavated soil, conditioned with foam, bentonite or polymers, as the support medium and removes it with a screw conveyor. A slurry machine supports the face with pressurised bentonite suspension and pumps the spoil to a separation plant. Slurry machines are generally used in permeable sands and gravels under water pressure, while EPB machines work best where the ground has enough fine material, or can be conditioned to behave as a paste.

What is a cutterhead intervention?

It is planned entry into the space behind the cutterhead to inspect or change cutting tools. On a closed-face machine the chamber may have to be kept under compressed air to support the face, so workers pass through an air lock and the work falls under the Work in Compressed Air Regulations 1996. BS 6164:2019 and ITA/BTS Report 10 give guidance on high-pressure interventions.

Is microtunnelling the same as pipe jacking?

They belong to the same family. In both, pipes are jacked from a drive shaft behind a shield to form a continuous string in the ground. Microtunnelling uses a steerable, remotely controlled shield at diameters too small for people to enter. The Pipe Jacking Association’s design guidance treats remote operation from the surface as the lowest-risk option.

Which standard covers the design of segmental tunnel linings?

PAS 8810:2016, Tunnel design – Design of concrete segmental tunnel linings – Code of practice, published by BSI on 30 April 2016. It brings segmental lining design guidance into one document but does not cover sprayed concrete or cast in situ linings, pipe jacking, cut-and-cover tunnels, or drill-and-blast and hard rock tunnelling. Health and safety during construction is covered by BS 6164:2019.

What training do people working on a TBM drive need?

It depends on the role and on what the principal contractor requires. Everyone needs a site induction. The CITB Tunnelling Safety Training Scheme gives a one-day, awareness-level introduction to tunnelling health and safety, and engineers who want the technical background can take an online course covering TBM tunnelling. Work in compressed air also involves medical assessment by an appointed doctor under the 1996 Regulations.

9

Sources

CPD Certified Online Course

Online Tunnel Engineering Course

Learn how TBM, pipe jacking, SCL and shaft projects are planned and built, at your own pace and from any location.

  • Format: Online and self-paced; start any time
  • Certificate: CPD certified
  • Content: 8 modules, from rock mechanics and drill and blast to TBM tunnelling, pipe jacking, conventional NATM/SCL tunnelling in soft ground and shafts
Call our course advisors: 01732 247780Email: hello@tetrainingacademy.co.uk