Published: 18 November 2026Reading time: 9 minutesSCL / NATMBTS SCL guide 2025

Sprayed Concrete Lining (SCL) and NATM Explained for UK Tunnelling

By TE Training Academy Editorial Team | Reviewed by Mehdi Hosseini, CEng FICE

Reviewed against: HSE's 1996 review Safety of New Austrian Tunnelling Method (NATM) Tunnels, HSE's 2000 report on the Heathrow collapse (as summarised in the trade press), the BTS guide Sprayed Concrete Linings in Soft Ground (2025), BS EN 14487-1:2022 and BS 6164:2019

Sprayed concrete lining (SCL) is used in the UK for tunnels and chambers whose shape or size does not suit a tunnel boring machine: station platforms, junctions, cross passages and enlargements. The British Tunnelling Society (BTS) notes that SCL was used for the five central stations on Crossrail, as well as crossovers and cross passages, because it can adapt to complex geometry that is impractical with TBMs.

This guide explains what NATM and SCL mean, how an SCL tunnel is excavated, supported and monitored, what the 1994 Heathrow collapse taught the industry, which standards apply and the safety controls that matter at the face.

1

What NATM is, and why UK practice says SCL

HSE’s 1996 review traces the English term “New Austrian Tunnelling Method” to articles by Professor L von Rabcewicz in Water Power in 1964 and 1965. They described a relatively thin sprayed concrete lining, used with other ground reinforcement such as rock bolts, to stabilise tunnels in rock. The lining was designed to move with the ground until a stable condition developed, and deformation measurements confirmed that it had.

HSE also found that there was no definition of NATM understood and agreed by everyone who used the term. For its review it described NATM as a tunnel built with open-face excavation and a lining of sprayed concrete, often with ground anchors, bolts and dowels.

In UK soft ground, especially London Clay, the method has developed away from its rock origins. The ICE’s 1996 design and practice guide was titled Sprayed concrete linings (NATM) for tunnels in soft ground, and the BTS’s 2025 best practice design guide uses “sprayed concrete linings” throughout. A Tunnels and Tunnelling commentary describes SCL emerging as the UK approach after the Heathrow collapse. In practice, SCL names what is built, while NATM is still used as a general label, and the ITA glossary treats the two terms as equivalent.

2

The excavation and support sequence

HSE’s 1996 review describes the basic cycle. The face is divided into smaller headings, typically a top heading (crown), bench and invert. Excavation advances in rounds of about one metre, and sprayed concrete is applied after each round to form a new panel of lining. Once the full ring is closed, significant ground movement normally stops.

The BTS’s 2025 guide adds current UK practice:

  • Advance length: the larger the face area and advance length, the greater the risk of instability. Full-face advances in soft ground are typically limited to 1 to 1.5 m, and ICE guidance suggests sub-dividing faces larger than 30 m².
  • Primary lining: the sprayed concrete primary lining gives immediate ground support.
  • Lattice girders: these steel frames guide the excavation profile, but fixing them means more lifting and work at the face, often at height. The guide says current UK practice is to design them out wherever possible.
  • Face support: a “toolbox” of measures such as ground treatment, dewatering, face dowels and spiles, pocket excavations and shorter advances keeps the face stable.

Rock bolts belong mainly to NATM’s hard rock origins; the BTS guide is written for soft ground and says it is not generally applicable to hard rock. Another option, used at Crossrail stations, is a pilot tunnel driven by SCL or by a TBM and then enlarged to full profile; the Crossrail enlargements used 1 m advance lengths.

3

Sprayed concrete: wet mix and fibre reinforcement

Sprayed concrete uses the same constituents as cast concrete, but the BTS guide notes that SCL mixes are usually high-performance mixes containing several admixtures, including accelerators. Mixes should be tested at the maximum and minimum accelerator content expected, and those limits kept to on site.

BS EN 14487-1:2022 covers both wet-mix and dry-mix sprayed concrete. For tunnelling at any scale, Tunnels and Tunnelling reports that there is little alternative to wet-mix, mechanised spraying to meet production needs, with dry-mix largely restricted to small tasks and repairs. Crossrail’s air quality guide likewise refers to wet-mix sprayed concrete on its SCL works.

Fibres: steel or macro-synthetic fibres give the concrete ductility and tensile resistance after cracking, but have limited effect before it cracks. BS EN 14889-1 and BS EN 14889-2 cover steel and polymer fibres for concrete.

Rebound: sprayed concrete that does not stick to the surface is called rebound. HSE’s review warns that if rebound is built into the lining it weakens it, so it should be treated as waste and cleared from the work area.

4

Monitoring, trigger levels and the observational method

Monitoring is central to SCL, but HSE’s 1996 review was clear about its limits. Its conclusions include:

  • monitoring is of limited value in the heading and does not ensure face stability, so every stage of excavation and lining should be designed;
  • the safety of completed linings depends on monitoring and interpreting the data, and the design should set the monitoring regime and contingency actions;
  • the observational method is a process in which a pre-determined design is reviewed during construction. It is not a method of design or design modification.

CIRIA’s report R185 describes the observational method as a continuous, managed, integrated process of design, construction control, monitoring and review, recognised in Eurocode 7.

The BTS’s 2025 guide sets out how trigger levels typically work for SCL, usually based on displacement:

  • Green: often around 70% of the predicted displacement; work is in a normal, safe condition.
  • Amber: set at the predicted displacement. Check instruments, inspect the structure and review monitoring, method and modelling, within 24 hours.
  • Red: set below the point at which the structure would fail. Carry out immediate checks and start a pre-planned response, which may include a controlled stop.

Who passes on information, who decides and how quickly should be agreed before work starts.

5

Waterproofing and the secondary lining

The BTS guide describes SCL tunnels as typically built in two phases: a sprayed concrete primary lining installed during excavation for immediate support, then a secondary lining with a waterproofing system. The secondary lining can be sprayed or cast in situ concrete.

The choice of lining configuration is closely linked to the waterproofing strategy:

  • Single shell: one lining takes temporary and permanent loads, typically only where water ingress is likely to be nil or low, or can be managed inside the tunnel.
  • Double shell: the primary lining is treated as temporary and the secondary lining is designed for all permanent loads, with no restriction on the waterproofing choice.
  • Combined shell: the two linings share the permanent loads, with the secondary lining typically taking the full water pressure; no bond is assumed between them.
  • Composite shell: a fully bonded waterproof membrane lets the two linings act together.

Where a sprayed secondary lining is placed over a sheet membrane, the guide says international experience suggests mesh or bar reinforcement to keep rebound to an acceptable level. ITAtech has published design guidance on spray-applied waterproofing membranes.

6

Lessons from the 1994 Heathrow Express collapse

On 20 and 21 October 1994, NATM tunnels under construction for the Heathrow Express at the Central Terminal Area of Heathrow Airport collapsed. The tunnels had been evacuated and nobody was injured, but buildings above were later demolished.

HSE published two key documents:

  • Safety of New Austrian Tunnelling Method (NATM) Tunnels: A review of sprayed concrete lined tunnels with particular reference to London clay (1996, reissued as a PDF in 2014), produced in response to the collapse;
  • The collapse of NATM tunnels at Heathrow Airport (2000), the report of HSE’s investigation, now listed as withdrawn.

Tunnels and Tunnelling’s review of the 2000 report describes a catalogue of errors in design, engineering management, construction and quality control. It highlights a central invert joint that was out of specification, and monitoring near an access shaft that showed continuing movement for months before the collapse.

In February 1999 at the Old Bailey, Balfour Beatty, which had pleaded guilty, was fined £1.2 million, and its NATM designer Geoconsult, convicted by a jury, was fined £500,000. The judge called it “one of the worst civil engineering disasters in the United Kingdom in the last quarter of a century”.

HSE’s 1996 conclusions still frame SCL safety: risks are greatest in the heading, open faces are hazardous, linings are most vulnerable before the ring is closed, and the method depends heavily on avoiding human failure.

7

Standards and guidance to know

  • BS 6164:2019, the code of practice for health and safety in tunnelling, which added guidance on exclusion zones for SCL tunnels.
  • Sprayed Concrete Linings in Soft Ground: A best practice design guide (BTS, 2025), open access, drawing on Crossrail and Transport for London station upgrades.
  • Sprayed concrete linings (NATM) for tunnels in soft ground (ICE, 1996).
  • BS EN 14487-1:2022 (definitions, specifications and conformity) and BS EN 14487-2:2006 (execution) for sprayed concrete, with the BS EN 14488 series for testing.
  • EFNARC European Specification for Sprayed Concrete and the BTS Specification for Tunnelling, fourth edition.
  • Crossrail’s Best Practice Guide on SCL exclusion zone management (2016).

A note on PAS 8810: PAS 8810:2016 is a code of practice for the design of concrete segmental tunnel linings. BSI lists tunnels lined with sprayed concrete among the things it does not cover, so it is not an SCL design standard.

The Online Tunnel Engineering Course includes a module on conventional NATM/SCL tunnelling in soft ground.

8

Key safety controls at the SCL face

Never work under unsupported ground or fresh concrete. Crossrail’s exclusion zone guide states that falling ground or immature (green) concrete is a major risk to people in SCL tunnels and that exclusion zones are the main way to prevent injury. An exclusion zone is an area that no one may enter under any circumstances, normally separated by a physical barrier from a restricted area open only to named people. A zone is released only after strength testing shows the concrete has reached a minimum strength set by the designer.

The cost of getting this wrong is real. On 7 March 2014 René Tkáčik was killed at Crossrail’s Fisher Street site when he was crushed by falling wet concrete. After an HSE investigation found a failure to properly enforce exclusion zones, BAM Ferrovial Kier was fined £1,065,000 in 2017 for his death and two other incidents, one of which involved a worker hit by pressurised water and concrete debris while concrete lines were being cleaned.

Rebound and dust: Crossrail’s air quality guide found inhalable dust to be the main hazard with SCL, from cement, microsilica, aggregates, accelerators and fibres. With adequate ventilation, respirable dust and quartz were generally kept below their workplace exposure limits. Preparing surfaces for the secondary lining, by sweeping or with air lances, can also raise significant dust.

Sprayer operation: spraying is skilled work. EFNARC runs a nozzleman certification scheme, and HSE’s review advised against additives that are aggressively harmful to people.

For an introduction to tunnelling site safety, see our CITB TSTS course and the full list on our tunnelling courses page.

9

Frequently asked questions

Is SCL the same as NATM?

They overlap. NATM began in rock tunnelling as a method in which a thin sprayed concrete lining and rock reinforcement move with the ground until it stabilises. In UK soft ground the method has developed differently, and the industry generally calls it sprayed concrete lining (SCL), which describes what is built. HSE found in 1996 that there was no definition of NATM agreed by all who used the term.

Why was the Heathrow Express collapse so significant?

It was one of the most serious UK civil engineering failures of its time. The October 1994 collapse led HSE to publish a review of NATM safety in 1996 and its investigation report in 2000. The contractor and its NATM designer were fined a combined £1.7 million in 1999. HSE’s findings on monitoring, quality and engineering management still shape UK SCL practice.

Does PAS 8810 apply to sprayed concrete linings?

No. PAS 8810:2016 is a code of practice for designing concrete segmental tunnel linings, and BSI lists tunnels lined with sprayed concrete among the things it does not cover. For SCL, the main references are the BTS guide Sprayed Concrete Linings in Soft Ground (2025), BS EN 14487-1:2022 and BS EN 14487-2:2006 for sprayed concrete, and BS 6164:2019 for health and safety.

What is an SCL exclusion zone?

It is an area near the working face that nobody may enter while ground or freshly sprayed concrete could fall. Crossrail’s best practice guide separates it from a restricted area, where only named people may go, using a physical barrier, and releases it only after testing shows the concrete has reached a minimum strength set by the designer. BS 6164:2019 added guidance on exclusion zones for SCL tunnels.

Why are lattice girders used less in UK SCL tunnels?

Lattice girders help guide the excavation profile, but installing them means more lifting and fixing and more work at the tunnel face, often at height. The BTS guide Sprayed Concrete Linings in Soft Ground (2025) says it is current UK practice to design them out wherever possible, reducing the time people spend in the most hazardous part of the tunnel.

10

Sources

CPD Certified Online Course

Online Tunnel Engineering Course

Study conventional NATM/SCL tunnelling in soft ground alongside TBM, drill and blast and shaft construction, at your own pace.

  • Format: Online and self-paced; start any time
  • Certificate: CPD certified
  • Content: 8 modules, from rock mechanics and drill and blast to TBM tunnelling, pipe jacking, conventional NATM/SCL tunnelling in soft ground and shafts
Call our course advisors: 01732 247780Email: hello@tetrainingacademy.co.uk