Reviewed against: DAUB Recommendations for the Selection of Tunnel Boring Machines (2022, revised 2025), BS 6164:2019 (BSI summary), PAS 8810:2016, the Work in Compressed Air Regulations 1996 and the ICE paper on Crossrail's machine-driven tunnels
A tunnel boring machine (TBM) excavates the ground, supports it and, in most modern machines, builds the tunnel lining as it advances. The German Tunnelling Committee (DAUB), the German member of the International Tunnelling and Underground Space Association, classifies TBMs as full-face machines, which excavate the whole cross-section with a cutterhead, or partial-face machines, which use an excavator arm or roadheader inside a shield.
This guide explains the main full-face machine types, how engineers choose between them, how the lining and back-up work, the hazards on a TBM drive and how TBMs have been used on three recent UK projects.
Three machine types are used where the face will stand up without active support. DAUB describes them as follows.
Gripper TBMs work in rock with a medium to long stand-up time. They have no full shield and give no active support to the face. To push the cutterhead forward, hydraulic gripper plates brace against the tunnel wall; at the end of each stroke the machine rests on a rear support while the grippers are reset. Disc cutters break the rock, and support such as anchors, steel arches or sprayed concrete is installed close behind the cutterhead.
A single (or open) shield is used for stable faces, for example firm clays or rock. The shield protects the excavation, a segmental lining ring is built inside it, and thrust cylinders push off the last completed ring.
A double shield has two telescopic parts: a front shield with the cutterhead and main thrust cylinders, and a gripper shield behind it. In stable rock the grippers take the thrust, so the segment ring can be built while the machine bores. Where the grippers cannot hold, the machine works in single-shield mode and thrusts off the segments.
Cutting rock produces dust, so DAUB says these machines need dust suppression, such as water sprays at the cutterhead, a dust shield and extraction with dedusting on the back-up.
In soft ground, and especially below the water table, the face has to be supported actively. Closed-face machines seal the excavation chamber behind the cutterhead with a pressure bulkhead and keep it under pressure.
An EPB machine can also run in open mode in stable ground, or in a transition mode with a partly filled chamber and compressed air. DAUB recommends that the machine type and operating mode are set for each section of the route, with a support pressure range for closed mode.
For utility tunnels and pipelines, the lining is often pushed into place rather than built. The International Society for Trenchless Technology defines a pipe jack as a system of installing pipes directly behind a shield machine by hydraulic jacking from a drive shaft, so that the pipes form a continuous string in the ground. Microtunnelling uses the same method with a steerable, remotely controlled shield, at diameters too small for people to enter.
BS 6164:2019 covers pipe and box jacking in its clause on excavation and control of ground movement. In 2024 the Pipe Jacking Association replaced its earlier designer guidance with Pipejacking design guidance for CDM Duty Holders, based on consensus with the British Tunnelling Society and intended to be read with BS 6164. Tunnels and Tunnelling’s summary reports that it rates excavation methods by risk against internal diameter and drive length: machines operated remotely from the surface are the lowest-risk option, while methods that need people to enter the smallest pipes are classed as not acceptable.
The guidance also notes that meeting these safety requirements may call for a larger internal diameter than the hydraulic design alone would need, and it prefers intermediate shafts to in-tunnel tool changes on small machines.
A shielded TBM builds the lining in rings of precast concrete segments, placed by an erector inside the tail of the shield, and the gap between the ring and the ground is filled with grout. Crossrail’s running tunnels show a typical arrangement. According to the ICE paper on the project’s machine-driven tunnels:
For design, PAS 8810:2016, Tunnel design – Design of concrete segmental tunnel linings – Code of practice, brings segmental lining guidance into one document. It excludes sprayed concrete and cast in situ linings, pipe jacking, and drill-and-blast and hard rock tunnelling.
The back-up train is the line of trailing gantries behind the shield that carries the equipment the machine needs to keep advancing. On modern drives it is long: each of HS2’s Chiltern tunnel machines was about 170 m long overall. On gripper machines, DAUB says rock support is completed in the back-up area and dust is extracted there. On the HS2 Chiltern drives, refuge chambers were provided on the TBMs as well as in the tunnel.
Machine selection starts with the ground. DAUB’s recommendations set out a step-by-step process:
Groundwater is often decisive. On Crossrail, six of the eight TBMs were EPB machines and two were slurry machines for the water-bearing Chalk aquifer. On HS2’s Chiltern tunnel, the contractor chose variable density machines because conventional low-density slurry could leak into fractures in the chalk and pollute the aquifer.
Settlement shapes how tightly the face is controlled. Crossrail assessed more than 17,500 third-party assets, generally specified 1.0% volume loss for the running tunnels and set tighter control zones of 0.5% or 0.75% in sensitive areas. The British Tunnelling Society’s guideline Closed-face tunnelling machines and ground stability (2005), published with the ICE, deals with choosing between EPB and slurry machines and managing ground stability in urban areas.
The main hazards on a TBM drive, and where the guidance deals with them, are:
Our CITB Tunnelling Safety Training Scheme course introduces tunnelling plant, the control of underground plant and emergency arrangements for people starting work underground.
In each case the machine type followed the ground and the groundwater.
The Online Tunnel Engineering Course covers TBM tunnelling and pipe jacking in more depth, and our tunnelling courses page lists all our tunnelling training.
Both support the face under pressure. An EPB machine uses the excavated soil, conditioned with foam, bentonite or polymers, as the support medium and removes it with a screw conveyor. A slurry machine supports the face with pressurised bentonite suspension and pumps the spoil to a separation plant. Slurry machines are generally used in permeable sands and gravels under water pressure, while EPB machines work best where the ground has enough fine material, or can be conditioned to behave as a paste.
It is planned entry into the space behind the cutterhead to inspect or change cutting tools. On a closed-face machine the chamber may have to be kept under compressed air to support the face, so workers pass through an air lock and the work falls under the Work in Compressed Air Regulations 1996. BS 6164:2019 and ITA/BTS Report 10 give guidance on high-pressure interventions.
They belong to the same family. In both, pipes are jacked from a drive shaft behind a shield to form a continuous string in the ground. Microtunnelling uses a steerable, remotely controlled shield at diameters too small for people to enter. The Pipe Jacking Association’s design guidance treats remote operation from the surface as the lowest-risk option.
PAS 8810:2016, Tunnel design – Design of concrete segmental tunnel linings – Code of practice, published by BSI on 30 April 2016. It brings segmental lining design guidance into one document but does not cover sprayed concrete or cast in situ linings, pipe jacking, cut-and-cover tunnels, or drill-and-blast and hard rock tunnelling. Health and safety during construction is covered by BS 6164:2019.
It depends on the role and on what the principal contractor requires. Everyone needs a site induction. The CITB Tunnelling Safety Training Scheme gives a one-day, awareness-level introduction to tunnelling health and safety, and engineers who want the technical background can take an online course covering TBM tunnelling. Work in compressed air also involves medical assessment by an appointed doctor under the 1996 Regulations.
Learn how TBM, pipe jacking, SCL and shaft projects are planned and built, at your own pace and from any location.

Sign in to book courses and manage your training.
Enter your email above, then we can send you a new verification link.
Don't have an account? Create one