Reviewed against: the Construction (Design and Management) Regulations 2015 (SI 2015/51) as reproduced in HSE L153, HSE's CDM 2015 dutyholder pages, the HSE Enforcement Policy Statement and GOV.UK guidance on the Building Regulations dutyholder regime
The Construction (Design and Management) Regulations 2015, known as CDM 2015, came into force on 6 April 2015. They apply to construction projects in Great Britain whether or not the project is notifiable, including work for householders. Rather than putting one person in charge of safety, they share legal duties between six dutyholders: the client, the principal designer, designers, the principal contractor, contractors and workers.
This guide sets out what each must do, with regulation numbers taken from the legal text reproduced in HSE’s guidance L153. It also covers F10 notification, the key project documents, welfare, the separate Building Regulations roles and HSE enforcement.
A client is any person for whom a project is carried out (regulation 2). Under regulation 4, a commercial client must:
Where there is, or is likely to be, more than one contractor, the client must appoint a principal designer and principal contractor in writing (regulation 5). If it does not, it must carry out their duties itself (5(3) and 5(4)).
A domestic client is one for whom the project is not carried out in the course or furtherance of a business (regulation 2). Under regulation 7, its duties in regulations 4(1) to (7) and 6 pass to the contractor, or to the principal contractor where there is more than one, unless the principal designer takes them on under a written agreement.
A designer is any person who, in the course of a business, prepares or modifies a design, or arranges for someone under their control to do so. Regulation 2 expressly includes clients and contractors when they design. Under regulation 9, a designer must:
The principal designer is a designer with control over the pre-construction phase, appointed in writing where there is more than one contractor (5(1)(a)). Under regulations 11 and 12 it must:
The principal contractor is a contractor appointed in writing to control the construction phase where there is more than one contractor (5(1)(b)). Under regulations 12 to 14 it must draw up the construction phase plan before the site is set up and keep it under review (12(1) and 12(4)); plan, manage, monitor and coordinate the construction phase (13(1)); organise cooperation between contractors (13(3)); ensure a suitable site induction, prevent unauthorised access and provide Schedule 2 welfare facilities (13(4)); liaise with the principal designer and pass on information for the health and safety file (13(5) and 12(7)); and consult and engage with workers (regulation 14).
Every contractor must plan, manage and monitor the work under its control (15(2)) and follow directions from the principal designer or principal contractor and the relevant parts of the construction phase plan (15(3)). It must only use people who have, or are gaining, the necessary skills, knowledge, training and experience (15(7)), provide supervision, instructions and information, including a site induction where needed (15(8) and 15(9)), prevent unauthorised access (15(10)) and meet Schedule 2 for its workers (15(11)). On a single-contractor project, it draws up the construction phase plan (15(5)).
Workers work for or under the control of contractors. HSE’s guidance says they must be consulted on matters affecting their health, safety and welfare, take care of their own and others’ safety, report anything likely to endanger anyone, and cooperate with other dutyholders. The reporting and cooperation duties are in regulations 8(5) and 8(4).
Under regulation 6(1), a project is notifiable if the construction work on a construction site is scheduled to:
The client must give notice in writing to HSE as soon as is practicable before the construction phase begins (6(2)). The notice must contain the particulars in Schedule 1, be clearly displayed in the construction site office where workers can read it, and be updated if necessary (6(3)). Certain railway work is notified to the Office of Rail and Road, and work on nuclear sites to the Office for Nuclear Regulation (6(4) and 6(5)).
HSE’s guidance in L153 adds some practical points:
Notification does not decide whether CDM 2015 applies. L153 states that its requirements apply whether or not the project is notifiable.
| Document | Who is responsible | When it is needed | Regulations |
|---|---|---|---|
| Pre-construction information | Client, assisted by the principal designer | Every project, as soon as practicable | 2, 4(4), 11(6) |
| Construction phase plan | Principal contractor, or the sole contractor | Every project, before the construction phase | 4(5)(a), 12, 15(5) |
| Health and safety file | Principal designer | Projects with more than one contractor | 4(5)(b), 12(5) to 12(10) |
Pre-construction information is information in the client’s possession, or reasonably obtainable, that is relevant to the work and proportionate to the risks. It covers the project, its planning and management, and health and safety hazards, including design and construction hazards and how they will be addressed (regulation 2).
The construction phase plan sets out the health and safety arrangements, site rules and specific measures for any work in the Schedule 3 categories of particular risk (12(2)).
The health and safety file holds information likely to be needed to keep people safe during later work on the structure (12(5)). HSE’s guidance says it is only required where there is more than one contractor. A client who disposes of its interest in the structure must pass the file to the new owner (4(7)). For how these documents work with temporary works, see our guide to CDM 2015 temporary works duties.
Schedule 2 sets the minimum welfare facilities for construction sites. The client’s arrangements must ensure they are provided (4(2)(b)), the principal contractor must provide them throughout the construction phase (13(4)(c)), and each contractor must meet them for its own workers (15(11)). The schedule covers:
Because the principal contractor’s duty runs throughout the construction phase, facilities need to be in place from the start of work on site.
The Building Safety Act 2022 led to a second set of roles with the same names. The Building Regulations etc. (Amendment) (England) Regulations 2023 (SI 2023/911) added Part 2A, on dutyholders and competence, to the Building Regulations 2010. They came into force on 1 October 2023 and apply in England.
| Aspect | CDM 2015 | Building Regulations Part 2A |
|---|---|---|
| Purpose | Health and safety of workers and anyone around the site | Design and building work complying with building regulations |
| Where it applies | Great Britain | England |
| In force | 6 April 2015 | 1 October 2023 |
| Principal designer | Plans, manages and monitors the pre-construction phase for health and safety | Plans, manages, monitors and coordinates design work so designs comply |
| Principal contractor | Plans, manages and monitors the construction phase for health and safety | Plans, manages, monitors and coordinates building work and must never accept non-compliant work |
GOV.UK guidance explains that the CDM principal designer and principal contractor can also carry out these roles for building regulations purposes. If they are the same, the client must confirm this in writing to those it appoints. Where different organisations hold the roles, they need to work together and share relevant information. The competence requirements differ under each regime, so clients should check competence for each role separately.
HSE is the enforcing authority for most construction projects, with the Office of Rail and Road and the Office for Nuclear Regulation covering certain rail and nuclear work. Fire authorities enforce some fire-related requirements where a site is within premises occupied by others (regulation 36). HSE’s Enforcement Policy Statement lists the options open to inspectors:
Failing to comply with a notice is itself a criminal offence. Where an inspector finds a material breach and says so in writing, HSE also charges a Fee for Intervention.
CDM 2015 does not name specific courses, but it does require competence (regulations 8 and 15(7)). Role-based training is one way to build and evidence it: SMSTS for site managers, SSSTS for supervisors, DRHS for directors, and our CDM Awareness course for anyone new to the regulations. See all our CITB courses.
Yes. HSE’s guidance states that CDM 2015 applies whether or not a project is notifiable, and it covers work for domestic clients. On domestic projects the client duties pass to the contractor, the principal contractor or, under a written agreement, the principal designer (regulation 7). The paperwork should be proportionate to the risks, but every project still needs a construction phase plan.
The client, under regulation 6, as soon as is practicable before the construction phase begins. It applies where work will last longer than 30 working days with more than 20 workers at any one time, or will exceed 500 person days. HSE’s guidance says the client may ask someone else to submit it on its behalf. For domestic clients, the duty passes to another dutyholder under regulation 7.
On a commercial project with more than one contractor, the client must carry out the principal designer duties in regulations 11 and 12 and the principal contractor duties in regulations 12 to 14 itself (regulations 5(3) and 5(4)). For a domestic client, the designer in control of the pre-construction phase becomes the principal designer and the contractor in control of the construction phase becomes the principal contractor (regulation 7(2)).
No. HSE’s guidance in L153 says a health and safety file is only required for projects involving more than one contractor. A construction phase plan, by contrast, is required on every project. On single-contractor work the contractor draws it up (regulation 15(5)); otherwise the principal contractor does (regulation 12(1)).
Yes. GOV.UK guidance says the CDM principal designer and principal contractor can also carry out those roles for building regulations purposes, and the client must confirm this in writing when they are the same. The competence requirements differ between the two regimes, so the client should check the appointee is competent for each role separately.
Book TE Training Academy’s one-day CDM Awareness course to build your understanding of the regulations and the duties of each dutyholder.

Sign in to book courses and manage your training.
Enter your email above, then we can send you a new verification link.
Don't have an account? Create one