Published: 18 November 2026Reading time: 9 minutesBS 5975-1:2024Design checks

Temporary Works Design Check Categories 0 to 3 Explained (BS 5975-1:2024)

By TE Training Academy Editorial Team | Reviewed by Mehdi Hosseini, CEng FICE

Reviewed against: BS 5975-1:2024 (BSI product information and February 2025 announcement), HSE temporary works guidance, CDM 2015 regulation 19, HBF Temporary Works Guidance (January 2025) and CITB temporary works materials.

Every temporary works design should be checked before it is built. How independent that check must be depends on the design check category, numbered 0 to 3. The category rises with the complexity and risk of the design, from a site check of a supplier’s standard solution up to a full check by a separate organisation.

The procedure sits in BS 5975, the UK code of practice for temporary works. At the end of 2024, BS 5975:2019 was replaced by two parts: BS 5975-1:2024 for management procedures and BS 5975-2:2024 for falsework design. This guide explains each category, who decides it, who signs the design check certificate and how the category feeds into the design brief and the temporary works register. It summarises the standard rather than reproducing it, so use your own copy of BS 5975-1:2024 for the exact wording.

1

Why temporary works designs are checked

Under regulation 19 of the Construction (Design and Management) Regulations 2015, any temporary support or temporary structure must be designed, installed and maintained to withstand the loads that may foreseeably be imposed on it, and used only for the purpose it was designed for. A design check is one of the main ways a contractor shows that duty has been met.

HSE’s guidance explains why the check matters. It says temporary works failures often result from loadings being underestimated, particularly where loads from the sides have not been considered. It also says that not every structural engineer can design temporary works: the designer needs temporary works training and experience. For more complex work, HSE says the design will also need to be checked by an independent party.

HSE is clear that the law does not require you to follow BS 5975 or to use the title Temporary Works Coordinator. HSE describes the BS 5975 approach as based on industry consensus on good practice. Our BS 5975 guide covers the wider procedure.

A design check looks at the concept, the adequacy and correctness of the design, and whether it meets the design brief. It should be done by a competent person who is independent of the people who produced the design. The more novel or complex the temporary works, the more capable and the more remote from the designer the checker should be. That principle is what the four categories put into practice.

2

The four design check categories and the independence each needs

The table below summarises the categories as set out in BS 5975 and reproduced in industry guidance such as the Home Builders Federation’s Temporary Works Guidance (January 2025).

↔ Scroll table horizontally to view all columns
CategoryScopeWho can carry out the check
0Restricted to standard solutions. The check confirms that site conditions do not conflict with the scope or limitations of the chosen solution.Another member of the site or design team, because this is a site issue.
1Simple designs, using simple methods of analysis in line with the relevant standards, supplier’s technical literature or other reference publications.Another member of the design team.
2More complex or involved designs, including those needing considerable interpretation of loading or soils information.An individual not involved in the design and not consulted by the designer.
3Complex or innovative designs, including unusual designs, significant departures from standards, novel methods of analysis or considerable engineering judgement.Another organisation. The check should include an overall check to assure co-ordination of the whole design.

Category 0 applies only to the use of a standard solution. The original design of that standard solution is a different matter: it needs its own structural calculations and a check at Category 1, 2 or 3, carried out by the organisation that publishes it.

For Category 2 and 3 checks, the checker should produce independent calculations rather than reworking the designer’s. CITB’s template design and check certificate treats the checker’s own calculations as mandatory at these two categories.

3

Typical examples for each category

The examples below come from HSE guidance and from the scope descriptions in the BS 5975 table. They are indicative only. The right category depends on the actual design and the risk it presents, not just on the type of temporary works.

Category 0

HSE gives a tower scaffold, or a trench box in a 2 m excavation in firm, dry ground, as examples of a standard solution for a small, straightforward job. Even then, the person organising the work must check the ground and confirm that the assumptions behind the standard solution apply on site.

Category 1

Simple designs such as formwork, falsework where top restraint is not assumed, and needling and propping to brickwork openings in single-storey construction.

Category 2

Excavations, including excavation support using sheet piles; foundations; structural steelwork connections; reinforced concrete; and designs where stability depends on restraint at the top of the temporary works, such as top-restrained falsework.

Category 3

Complex or innovative designs that result in complex sequences of moving or constructing either the temporary works or the permanent works. The HBF guidance also places basement excavations and tunnels in this category.

Where there is doubt between two categories, the safer course is the higher one. Agree the choice early, because it affects the time and cost of the check.

4

Who decides the category and who issues the design check certificate

Several roles are involved. Their titles come from BS 5975, but your organisation’s temporary works procedure should name the people and confirm who does what.

  • Designated Individual (DI): the senior person in each organisation responsible for its temporary works procedure. The DI appoints Temporary Works Coordinators and Supervisors and makes sure they are competent.
  • Temporary Works Coordinator (TWC): makes sure suitable designs are prepared, checked and correctly erected on site. The TWC issues the design brief to the designer and confirms the level of checking required.
  • Temporary Works Designer: produces the design and agrees the check category with the TWC. The designer’s input matters because the category affects the level and quantity of design output.
  • Design checker: carries out the check at the required level of independence.
  • Temporary Works Supervisor (TWS): assists the TWC with day-to-day supervision and checks on site, as delegated by the TWC.

Larger design organisations may also have someone who coordinates temporary works design and checking internally, sometimes called a temporary works design coordinator. Be careful with abbreviations: many company procedures and guides use TWDC for the temporary works design checker instead. Your procedure should say which is meant.

The design check certificate

The certificate is signed by the designer and the checker. It is expected for Category 2 and 3 checks, and an organisation may also require one for Category 1. It states the category of check and identifies the drawings and specification checked. The TWC’s job is to make sure it is in place, and that it refers to the drawings actually being used, before the temporary works are loaded.

5

How the category links to the design brief and the temporary works register

The design brief is the starting point for the design, the calculations, the drawings and the design check. It should contain all the information relevant to the design and be prepared early enough to leave time for design, checking, procurement and construction. For a small, low-risk item it may be short; for a deep excavation it may need a large amount of information.

The check category should be agreed at an early stage, with advice from the designer, because it affects the scope of the design output. It may not be known when an item is first entered on the register, but it should be recorded as soon as it is decided. Many organisations include a proposed category in the design brief so the designer and checker can plan resources.

The HBF guidance lists what a temporary works register should record for each item, including:

  • reference number, short description and risk classification;
  • date the design brief was issued and the date the design is needed;
  • designer and design checker (company and individual);
  • design check category;
  • dates the design was completed, and checked and approved;
  • date of the permit to load and, where needed, the permit to unload; and
  • third-party approvals.

The register then links the paperwork to the site. Before a permit to load is issued, the TWC or an authorised TWS should confirm that the temporary works match the certified design, that the drawings used are the ones on the certificates, that any changes have been approved by the designer, and that ground, water and use are as the design assumed. Our register and design brief guide has a worked template.

6

Did BS 5975-1:2024 change the design check categories?

According to BSI, BS 5975-1:2024 and BS 5975-2:2024 together replace BS 5975:2019, which was split in two. Sections 1 and 2 of the 2019 edition became Part 1, which covers procedural controls for all temporary works. Section 3 became Part 2, which covers falsework design and implementation. Design checking is part of managing temporary works, which is the subject of Part 1.

BSI’s announcement of the revision, in February 2025, listed the main technical updates as:

  • maximum wind force calculation;
  • guidance on permissible stress;
  • limit state design of all falsework; and
  • the extent of control measures required on projects of different sizes.

Neither BSI’s summary nor the trade press coverage reports any change to the design check categories. Industry guidance published after the revision, such as the HBF’s January 2025 guidance, still uses the same four categories with the same levels of independence. In practice, the categories carried over from BS 5975:2019. HSE’s temporary works guidance now refers to the two 2024 parts.

Update your procedures, design briefs, register templates and certificates so they cite BS 5975-1:2024 rather than BS 5975:2019, and check the wording against your copy of the current standard.

For a fuller comparison of the editions, read BS 5975:2019 vs BS 5975-1 and -2:2024.

7

Common mistakes with design check categories

Most problems with design checks are procedural rather than mathematical. These are the ones that HSE and industry guidance warn about most often:

  • Treating Category 0 as no check. A standard solution still needs a check that site conditions, loading and use are within its stated limits, including the ground conditions and groundwater for trench support.
  • Changing a standard solution. Substituting components, or using the equipment outside the supplier’s limits, takes it outside the standard solution, so it can no longer be treated as Category 0.
  • Setting the category too late. Leaving it until the design is finished can mean the check is under-resourced or the programme slips.
  • Choosing by item type alone. An excavation can be simple or complex. The category should reflect the actual design risk.
  • A checker who is not independent enough. At Category 2 the checker must not have been involved in, or consulted on, the design. At Category 3 the check should come from another organisation.
  • Checking the wrong drawings. The certificate must refer to the drawings and specification actually issued for construction, and any later change needs the designer’s approval.
  • An out-of-date register. If the category, checker and certificate dates are not recorded, the TWC cannot show the item was ready to load.
  • Underestimating loads. HSE highlights lateral loads in particular.

Coordinators who manage these decisions can train on the CITB Temporary Works Coordinator course, with the TWC Refresher for existing certificate holders. Site staff who support them can take the Temporary Works Supervisor course. All are listed on our CITB courses page.

8

Frequently asked questions

Does a Category 0 standard solution still need a design check?

Yes. Category 0 is a site check rather than a check of the original design. Someone in the site or design team confirms that the site conditions, loading and use fall within the scope and limitations of the standard solution. HSE’s example of a trench box in a 2 m excavation still needs the ground checked to confirm the solution’s assumptions apply.

Can someone from the same company check a Category 2 design?

BS 5975 does not require a different organisation at Category 2. It requires the check to be carried out by an individual who was not involved in the design and was not consulted by the designer. That person can work for the same organisation, provided that independence is real and recorded. Category 3 checks should be carried out by another organisation.

Who signs a temporary works design check certificate?

The designer and the design checker sign it. It is expected for Category 2 and 3 checks, and an organisation may require one for Category 1 as well. The certificate states the category of check and identifies the drawings and specification checked. The Temporary Works Coordinator should make sure it is in place before the works are loaded.

Who decides the design check category?

The category is agreed between the Temporary Works Coordinator and the temporary works designer at an early stage, within the procedure set by the organisation’s Designated Individual. It is based on the complexity of the design and the risk it presents. Once decided, it is recorded on the temporary works register and, in many organisations, in the design brief.

Did BS 5975-1:2024 change the design check categories?

No change to the categories has been reported. BSI’s summary of the 2024 revision describes splitting BS 5975:2019 into two parts and technical updates mainly affecting falsework design, such as wind force and limit state design. Guidance written after the revision still uses categories 0 to 3 with the same levels of independence. Check the wording in your own copy of BS 5975-1:2024.

9

Sources

CITB Approved Training Organisation

Train as a Temporary Works Coordinator

Prepare for the Temporary Works Coordinator role on CITB’s two-day Site Safety Plus course.

  • Duration: 2 days
  • Format: Live online virtual classroom or London classroom
  • Certificate: CITB Site Safety Plus certificate, valid for 5 years
Call our course advisors: 01732 247780Email: hello@tetrainingacademy.co.uk