Reviewed against: BSI's published summaries of BS 6164:2019, the Construction (Design and Management) Regulations 2015, the Work in Compressed Air Regulations 1996 and HSE guidance on compressed air and good practice
Tunnelling brings several serious hazards together in a confined space: unstable ground, poor air, heavy plant, fire and, on some jobs, work under pressure. BS 6164 is the British Standard code of practice that sets out recommended controls for tunnelling in the UK construction industry.
This guide explains what the 2019 edition is, what it covers, how it sits alongside the Construction (Design and Management) Regulations 2015 (CDM 2015) and HSE’s approach to enforcement, and where the CITB Tunnelling Safety Training Scheme (TSTS) fits for people starting work underground. It summarises the standard rather than reproducing it, so anyone with duties on a tunnelling project should work from a licensed copy.
BS 6164:2019, Health and safety in tunnelling in the construction industry – Code of practice, was published by BSI on 31 October 2019. It superseded BS 6164:2011, which has been withdrawn. BSI says the revision takes account of advances in tunnelling technology and equipment, new techniques, and changes in health, safety and environmental legislation and guidance.
As a code of practice it gives recommendations and guidance, not legal requirements. HSE was represented on the drafting committee and contributed to the text.
BS 6164 is not a standalone document. BSI’s summary says it depends heavily on other publications, including:
BSI also notes that the International Tunnelling and Underground Space Association (ITA) and the engineering insurers’ association IMIA use BS 6164 as the default standard in their code of practice for risk management of tunnel works.
BSI’s product page notes an error in Table 8 of the 2019 edition: the sulfur dioxide exposure limits are stated incorrectly. BSI gives the correct values as 0.5 ppm (long-term limit) and 1.0 ppm (short-term limit).
BS 6164 deals with the health and safety of people engaged in tunnelling and of anyone who could be affected by it. According to BSI, it makes recommendations and gives guidance on:
It does not apply to shafts or tunnels constructed for mineral extraction.
BSI’s published summary does not list caverns by name; it refers to “other forms of underground construction”. If a project includes a cavern or another large underground chamber, check the scope clause of the standard itself before relying on it.
Two changes in the 2019 edition matter for smaller-diameter and shaft work. The clause on excavation and control of ground movement now covers soft ground, hard rock, and pipe and box jacking. The shafts clause was substantially extended and includes a formal definition of when a shaft should be treated as a confined space. Where it is, the Confined Spaces Regulations 1997 apply, including the need for emergency arrangements to be in place before anyone enters.
The choice of method, the lining design, the ventilation strategy and the emergency arrangements all need to be settled before the first advance. BS 6164:2019 reflects this with expanded guidance on design checking. BSI’s summary says that:
Tunnels and Tunnelling’s review of the revision notes that this guidance on checking lining designs extends to temporary linings as well as permanent ones.
The ground clause was rewritten under the title “Excavation and control of ground movement”, and guidance on ground improvement, including ground freezing and grouting, now sits in its own clause.
On larger projects, risk management also follows the ITA and IMIA code of practice for risk management of tunnel works, which uses BS 6164 as its default standard. For the temporary works side of tunnelling, see our article on the British Tunnelling Society and temporary works training.
CDM 2015 requires every place of construction work to have a sufficient supply of fresh or purified air, and plant used to provide it must warn of any failure where this is needed for health or safety. Crossrail’s best practice guide on air quality lists the typical hazards on tunnel drives:
CDM 2015 regulation 29 requires suitable steps to prevent injury from fire or explosion and from substances liable to cause asphyxiation, so gas monitoring needs to be planned, with alarm levels and the response to each alarm agreed in advance. The 2019 edition of BS 6164 goes further and recommends real-time monitoring of health hazards such as dust and diesel particulate, not only of safety hazards such as oxygen deficiency and flammable gas.
Two health changes stand out:
The Control of Substances Hazardous to Health Regulations 2002 (COSHH) apply to all of these exposures.
Escape from a tunnel can mean a long walk through smoke, so fire prevention and emergency planning carry particular weight. CDM 2015 sets the legal baseline: regulation 30 requires emergency procedures, regulation 31 emergency routes and exits, and regulation 32 suitable fire-fighting equipment and fire detection and alarm systems where they are needed.
BS 6164:2019 adds detailed guidance on plant. Its fire protection clause covers mobile and static equipment, including tunnel boring machines (TBMs), roadheaders and surface plant taken underground, such as excavators, generators and compressors. It recommends extinguishing agents for fixed fire suppression systems according to the plant being protected and refers to the need for cooling to prevent re-ignition. The revision also addresses lithium and other heavy-metal batteries in vehicles, including the highly toxic emissions they give off in a fire and the difficulty of extinguishing them.
A recent UK incident shows why these arrangements matter. On 10 May 2022 a personnel vehicle caught fire in one of the HS2 Chiltern tunnel drives. Nobody was injured, but three people working on the TBM, about 4.1 km into the tunnel, stayed in the machine’s refuge chamber for more than 12 hours, in contact with the surface, until it was safe to walk out. The contractor’s own account lists the arrangements in place: a fire risk assessment, a detailed emergency plan, fire-fighting provision on plant, refuge chambers on the TBMs and in the tunnel, self-rescue masks and call-out arrangements with the emergency services.
Some tunnels and shafts are driven, or entered for maintenance, under compressed air to hold back groundwater. This work is governed by the Work in Compressed Air Regulations 1996, which came into force on 16 September 1996. Key points include:
CDM 2015 applies too, and HSE notes that the compressed air contractor is usually the principal contractor. Schedule 3 of CDM 2015 lists work in caissons with a compressed air atmosphere among the types of work involving particular risks.
HSE’s former guide to the Regulations (L96) has been withdrawn, but the Regulations themselves are unchanged. HSE now points readers to guidance on the British Tunnelling Society’s website, which publishes good practice guidance on work in compressed air.
BS 6164:2019 includes guidance on high-pressure compressed air for cutterhead interventions for the first time. This specialist work takes place at pressures above national statutory limits, so it needs approval or an exemption from the regulator. The ITA/BTS Compressed Air Working Group’s Report 10, last revised in 2024, gives good practice guidance for it.
BS 6164 covers the main construction methods and the services that keep a tunnel running. Points to note from the 2019 edition and related legislation:
CDM 2015 is the legal framework for tunnelling projects. Its definition of “excavation” includes any earthwork, trench, well, shaft, tunnel or underground working, and Schedule 3 lists work on wells, underground earthworks and tunnels as work involving particular risks. Clients, principal designers, principal contractors, designers and contractors all keep their usual duties; our guide to CDM 2015 duties and legal liabilities covers them in more detail.
BS 6164 is not law, but HSE expects duty holders to apply relevant good practice as a minimum when it judges compliance, and it counts recognised standards as good practice. Enforcement follows when controls fail: in 2017 the Crossrail joint venture BAM Ferrovial Kier was fined £1,065,000 after an HSE investigation into the death of a worker crushed by falling wet concrete, and two other incidents, found a failure to properly enforce exclusion zones.
The CITB Tunnelling Safety Training Scheme (TSTS) sits at the other end of the scale. CITB describes it as a one-day, awareness-level course within its Site Safety Plus scheme. Its topics include tunnelling-related confined spaces, shaft and surface operations, tunnel construction, tunnelling plant and equipment, control of underground plant and emergency arrangements. It does not replace a project induction or the competence needed for a specific role. The CITB TSTS certificate is valid for three years.
TE Training Academy runs the CITB TSTS course in a classroom or virtual classroom. For engineers who need the technical background, the Online Tunnel Engineering Course covers TBM, drill and blast and SCL tunnelling. Both are listed on our tunnelling courses page.
No. BS 6164:2019 is a code of practice, so it gives recommendations and guidance rather than legal duties. The duties come from the Health and Safety at Work etc. Act 1974, CDM 2015, the Work in Compressed Air Regulations 1996 and other regulations. HSE expects duty holders to apply relevant good practice, including recognised standards, as a minimum, so in practice BS 6164 is the benchmark that tunnelling arrangements are judged against.
The current edition is BS 6164:2019, published by BSI on 31 October 2019. It superseded BS 6164:2011, which has been withdrawn. BSI has also flagged an error in Table 8, where the sulfur dioxide exposure limits are stated incorrectly; its product page gives the correct values. Buy the standard from BSI or access it through a licensed subscription so that you work from the full text.
Yes, in part. BSI’s summary says the clause on excavation and control of ground movement covers pipe and box jacking as well as soft ground and hard rock tunnelling. The Pipe Jacking Association’s design guidance for CDM duty holders, agreed with the British Tunnelling Society, is intended to be read alongside BS 6164 and deals with drive lengths, diameters and the risks of people entering small-diameter pipes.
CITB describes TSTS as a one-day, awareness-level course that introduces tunnelling health and safety, so it suits people starting work in or around tunnels and shafts and those who visit or supervise underground work. Check what the principal contractor requires for site entry, because a project induction and role-specific training are still needed. TE Training Academy runs the course in a classroom or virtual classroom.
No. Work in compressed air is governed by the 1996 Regulations, which require the compressed air contractor to give notice of the work at least 14 days before it starts, unless it was unforeseen, and to appoint a Contract Medical Adviser. BS 6164 sits alongside them and, since 2019, includes guidance on high-pressure compressed air for cutterhead interventions. HSE points to British Tunnelling Society guidance for detailed good practice.
A one-day introduction to tunnelling health and safety for people starting work in tunnels and shafts, from a CITB Approved Training Organisation.

Sign in to book courses and manage your training.
Enter your email above, then we can send you a new verification link.
Don't have an account? Create one